Increasing Central Pump Station Capacity of Khuzestan Steel Complex

Project Description

Client: Khuzestan Steel Complex
Date : Completed

  • Concret: 2000 m3
  • Reinforcement: 1500 m2
  • Formatting Weight: 2000 Kg
  • Procurement, transporting and
  • installation off valves, cranes,
  • pumps, transformers, MV & LV
  • Earth Work: 3000 m3