Construction of Pump Station and Water Pipelines to Shadegan Complex
Project Description
Client: Shadegan Steel Complex
Date : Completed
- Earth Work: 30000 m3
- Concret: 2000 m3
- Reinforcement: 1500 m2
- Formatting Weight: 40000 Kg
- Constructing pumping station in 10m depth with sheild plate operation
- Construction and installation of LV switchgear panel
- PLC and HMI
- Procurement and installation of 400-150 Siemens pumps, 1500 rpm, 75 kg
- Procurement and installation of instrumentation systems and mechanical screens
- Procurement, transporting and pipe laying with 1600 dia. pipes in 110m length
- Procurement, transporting and pipe laying with 400dia. pipes in 4850m length
- Operation of shield plate for lateral building D1200